Conversion of L5 office area to retail with the inclusion of new escalators inserted through the Harrington St facade on Level 5 and dropped into place over existing L4 escalators
Demolition and re-fit of all building services including air-conditioning, electrical and fire which incorporated a new smoke exhaust system
Total re-fit of all internal finishes and new brand boutique tenancies to an area in excess of 6000 square meters.
The entire project was carried out in stages to accommodate continued trading by DFS and occupation by office tenancies